D61 Piešťany - Horná Streda1980-1985

D61 Piešťany - Horná Streda

Stretch length: 8.3 km. Parts of the project are 8 bridges, of which 3 are found on the motorway; there are 3 overbridges and 2 bridges are located outside the motorway. The bridges were constructed of pre-cast members. The executed earthwork presented a volume of 1.58 million cubic metres. The quantity placed locally was 54 000 square metres of cement stabilisation layer and 48 000 tonnes of asphalt mixture.