A road construction project involving the Nowohuckiej route in Kraków; Class 1 Road from the Bieżanów junction to the junction of Christo Botewa, Rybitwy, Poland.
Section executed by Doprastav: Flyover E1 on S-7 that bridges the Zarzyckiego Street, a railway line and the River Serafa and other professional work such as water supply, sewerage, and gas networks.
E1 Flyover length : 256.67 m
Bridge type : pre-stressed bridge on sleepers
Total length : 256.67 m
Width : 40.1 m
Slab thickness : 0.25 m
Total bearing system height : 1.5 m
Number of spans : 7
Length of spans : 27 m, 37 m, 36 m, 36 m, 36 m, 36 m, 26 m